From 6am Monday 29 January to 6pm Friday 1 March 2024, there will be temporary traffic changes on Mary Street near the main station entrance site (Lot 1) boundary to construct permanent utility services for the new Albert Street station.
These activities will be carried out Monday to Sunday 24-hours for the duration of the work.
Works will include:
Earthworks and excavation adjacent to Lot 1.
Installation of utility services.
Removal of the Mary Street gantry.
Detours and traffic control will be in place to assist motorists and pedestrians. Access to properties will be maintained throughout the work including outside Mantra on Mary (refer map below).
Above: Mary Street work area, pedestrian and vehicle detour map.