Batter Slope Restoration Works – Mount Crosby Road, Mount Crosby

Mount Crosby Road, Mount Crosby
Batter Slope Restoration Works

UPDATE: February 2023

The Department of Transport and Main Roads (TMR) will be completing works to restore the batter slope along Mount Crosby Road, near Kholo Creek bridge, from late February 2024 to late April 2024. These works are to repair the batter slope after the February 2022 flood event.

Work activities

  • Batter slope restoration works
  • Removal of fallen debris and vegetation
  • Regrading of the slope
  • Installation of hydromulch-bonded fibre matrix(BFM)treatment

Timing

  • Works will commence late February and be completed in late April 2024, construction and weather conditions permitting.
  • Typical construction hours will be from 6:30am to 5:30pm, Monday to Friday.
  • While most of these works will be undertaken during the day, some Saturday and out of hours works may be required.

Expected impacts

  • Nearby residents and businesses can expect increased noise and dust.
  • Traffic changes including delays, localised traffic detours, road and lane closures and reduced speed limits.
  • Please allow extra time when planning your travel and follow the directions of roadside signage and traffic controllers.
  • A qualified arborist will be engaged to supervise the removal of trees in a way which minimises the impact to remaining vegetation.
  • Fauna spotter catchers will be in place throughout the tree and vegetation clearing to relocate any wildlife.

Every effort will be made to minimise impacts on the local community and surrounds.

For more information, please contact the Project Team by emailing metropolitanregion@tmr.qld.gov.au or call 3066 4338 during business hours. For up-to-date information on road closures and traffic conditions across Queensland, go to www.qldtraffic.qld.gov.au or call 13 19 40.

Assistance will be provided through the jointly funded Commonwealth-State Disaster Recovery Funding Arrangements (DRFA).

ORIGINAL: November 2023

The Department of Transport and Main Roads (TMR) will be completing batter slope restoration works along Mount Crosby Road, Mount Crosby, near the Kholo Creek bridge from from mid-November 2023 to late January 2024.

Works will include:

  • Batter slope restoration works
  • Removal of fallen debris and vegetation
  • Regrading of the slope
  • Installation of the hydromulch-bonded fibre matrix (BFM) treatment

Timing

  • Works will commence mid-November 2023 and be completed in late January 2024, construction and weather conditions permitting.
  • Typical construction hours will be from 6.30am to 5.30pm, Monday to Friday.
  • While the majority of the works will be undertaken during the day, some Saturday or other out of hours works may be required.

Expected impacts

  • Nearby residents and businesses can expect to experience short-term impacts including increased noise, and dust, during the works.
  • Traffic changes will be in effect, including localised traffic detours, road closures with traffic control, changes to traffic flow, temporary speed reductions and short-term traffic disruptions.
  • Please allow extra time when planning your travel and follow the directions of roadside signage and traffic controllers.
  • A qualified arborist will be engaged to supervise the removal of trees in a way which minimises the impact to remaining vegetation.
  • Fauna spotter catchers will be in place throughout the tree and vegetation clearing to relocate any wildlife as necessary.

Every effort will be made to minimise impacts on the local community and surrounds.

Assistance will be provided through the jointly funded Commonwealth-State Disaster Recovery Funding Arrangements (DRFA).

TMR appreciates your patience and cooperation while these important works are carried out.

The event is finished.

Date

26 Feb 2024 - 26 Apr 2024
Expired!

Time

6:30 am - 5:30 pm
Category

Organizer

Department of Transport and Main Roads
Phone
13 19 40
Website
http://www.qldtraffic.qld.gov.au