Batter Slope Restoration Works – Deagon Deviation, Deagon

Deagon Deviation, batter slope restoration works

UPDATE: February 2024

The Department of Transport and Main Roads (TMR) would like to advise that batter slope flood repair works will be carried out at two sites along the Deagon Deviation southbound from late February to early April 2024 as per the map below.

Works will include:

Site 1

  • Removal of fallen debris.
  • Installation of grouted rock pitching at the toe of the pedestrian bridge abutment.

Site 2

  • Removal of fallen debris and vegetation.
  • Installation of a hydromulch-bonded fibre matrix treatment to control erosion and promote growth.
  • Trees and other vegetation located within the treatment area and slope will be removed as part of the restoration works.

Timing

  • Works will commence late February and be completed by early April 2024, construction and weather conditions permitting.
  • Typical construction hours will be from 6:30pm to 4:30am, Sunday to Thursday.
  • Night works are required for road user safety, and to avoid what would otherwise be extensive traffic queuing and disruption to the road network.
  • While majority of the works will be undertaken at night, some Saturday or out of hours works may be required.

Expected impacts

  • Traffic changes will be in effect, including partial road shoulder closures, temporary speed reductions and short-term traffic disruptions.
  • Please allow extra time when planning your travel and follow the directions of roadside signage and traffic controllers.
  • Nearby residents and businesses can expect to experience short term impacts including increased noise, dust and odour during the works.

Upon completion, TMR officers will continue to review the site for up to three months. During this time, TMR will assess the work undertaken for longevity and quality. In some cases TMR may need to request further work at the location to rectify any defects.

Every effort will be made to minimise impacts on the local community and surrounds.

Assistance will be provided through the jointly funded Commonwealth-State Disaster Recovery Funding Arrangements (DRFA).

TMR appreciates your patience and cooperation while these important works are carried out.

ORIGINAL: November 2023

The Department of Transport and Main Roads (TMR) would like to advise that batter slope flood repair works will be carried out at two sites along the Deagon Deviation southbound from late November to mid-December 2023 as per the map below.

Works will include:

Site 1

  • Removal of fallen debris.
  • Installation of grouted rock pitching at the toe of the pedestrian bridge abutment.

Site 2

  • Removal of fallen debris and vegetation.
  • Installation of a hydromulch-bonded fibre matrix treatment to control erosion and promote growth.
  • Trees and other vegetation located within the treatment area and slope will be removed as part of the restoration works.

Timing

  • Works will commence late November and be completed by mid-December 2023, construction and weather conditions permitting.
  • Typical construction hours will be from 6:30pm to 4:30am, Sunday to Thursday.
  • Night works are required for road user safety, and to avoid what would otherwise be extensive traffic queuing and distruption to the road network.
  • While majority of the works will be undertaken at night, some Saturday or out of hours works may be required.

Expected impacts

  • Traffic changes will be in effect, including partial road shoulder closures, temporary speed reductions and short-term traffic disruptions.
  • Please allow extra time when planning your travel and follow the directions of roadside signage and traffic controllers.
  • Nearby residents and businesses can expect to experience short term impacts including increased noise, dust and odour during the works.

Upon completion, TMR officers will continue to review the site for up to three months. During this time, TMR will assess the work undertaken for longevity and quality. In some cases TMR may need to request further work at the location to rectify any defects.

Every effort will be made to minimise impacts on the local community and surrounds.

Assistance will be provided through the jointly funded Commonwealth-State Disaster Recovery Funding Arrangements (DRFA).

TMR appreciates your patience and cooperation while these important works are carried out.

The event is finished.

Date

19 Nov 2023 - 14 Dec 2023
Expired!

Time

6:30 pm - 4:30 am
Category

Organizer

Department of Transport and Main Roads
Phone
13 19 40
Website
http://www.qldtraffic.qld.gov.au
Menu